Garage Power Washing
CampusParc will begin its annual power washing of parking decks, stairwells and common areas in campus garages on March 21, 2026.
When work will occur:
-
Overnight hours or weekends to reduce disruption
-
Cleaning begins at 7 p.m.
-
The project will continue through August as part of CampusParc’s ongoing maintenance program
-
Duration varies depending on garage size
What to expect:
-
Garages will remain open, but select floors will close on a rolling basis for cleaning
-
Once one floor is completed, the next floor will close until all levels are finished
Important reminder:
-
Vehicles left on closed floors may be relocated at the owner’s expense
-
CampusParc will attempt to contact the vehicle owner before relocation.
-
Please ensure your MyAccount profile has a current phone number and email on file, as CampusParc will use this information to reach you before relocating your vehicle
Annual Maintenance Program
CampusParc will begin its annual preventative maintenance program for campus parking garages starting Monday, May 11. This program includes improvements to the stairwell towers, floor membrane repairs and replacement, concrete and other miscellaneous repairs throughout the garages.
What to expect:
-
Work may take place during the day, overnight, and/or on weekends to reduce disruption
-
Project length varies depending on the size of the garage and the scope of maintenance
-
This work is part of CampusParc’s ongoing maintenance program and will continue throughout the summer
Below is the tentative schedule for each garage, including the expected impacts.
|
Location |
Preventative Maintenance Dates and Spaces Closed* |
Power Washing Dates and Spaces closed* |
Alternative Parking Options |
|
SAFEAUTO Garage |
May 11 – June 16 125 spaces June 17 - June 22 417 spaces (L5 - L8) June 23 - August 7 125 spaces |
August 19-23 Weekend closure |
Patients/Visitors: |
|
Neil Avenue Garage |
May 11 – August 14 50 spaces |
July 20-23 July 26-27 Rolling Space Closure |
|
|
12th Avenue Garage |
May 11 – August 14 120 spaces |
August 28-30 Rolling Space Closure |
|
|
Arps Garage |
May 26 – May 28 50 spaces May 29 – June 1 785 spaces June 2 – June 4 50 spaces June 5 – June 8 785 spaces June 9 – June 17 491 spaces June 18 – June 21 - 785 spaces June 22 – August 14 - 491 spaces (L4 - L6 closed)
|
August 14-17 Rolling Space Closure |
A and BG5 Permits: |
|
Ohio Union South Garage |
May 11 – August 14 150 spaces June 25-28: L4 and L5 (270 spaces) Full Closure: July 9-12
|
August 25 - 27 Rolling Space Closure |
A Permits: BG5 Permits: Visitors: |
|
Gateway Garage |
May 11 – August 14 550 spaces, L4 & L5 closed |
August 14 - 17 Rolling Space Closure |
A Permits: |
|
Lane Avenue Garage |
May 11 – May 24 200 spaces May 25 - June 7 250 spaces June 8 - June 17 200 spaces June 18 - June 21 Full Closure June 22 - August 7 200 spaces |
July 31 August 1 August 4-9 Rolling Space Closure |
BG4 Permits: |
|
Wexner Medical Center Garage |
N/A |
May 23-24, May 27-30 June 1, 3, 4, 6 Rolling Space Closure |
Patients/Visitors: |
|
Northwest Garage |
N/A |
June 8-11 Rolling Space Closure |
A Permits: |
|
Tuttle Garage |
N/A |
June 15, 17-20, 22 Rolling Space Closure |
A and BG1 Permits: Visitors: |
|
Ohio Union North Garage |
N/A |
June 29, 30 July 1-2 Rolling Space Closure |
A Permit Holders: |
|
West Lane Garage |
N/A |
July 30 Rolling Space Closure |
A and BG4 Permits: |
|
11th Avenue Garage |
N/A |
August 10-12 Rolling Space Closure |
A and CG3 Permits: Patients/Visitors: |
*Please note: Dates are subject to change. Additional garage access will not be granted to other garages during power washing unless a garage is fully closed.
We apologize for any inconvenience this may cause and appreciate your understanding as we work to improve the garage's condition as part of our annual maintenance plan.
Surface Lot Maintenance
What’s happening:
Surface parking lot renovations take place annually, after the spring semester ends, as part of CampusParc's preventive maintenance program. Scheduling this work during the summer helps reduce the impact on customers, as fewer students, faculty, and staff are on campus.
What the work includes:
-
Asphalt repairs
-
Crack filling and sealing
-
Lot striping
-
Some lots will receive a combination of these improvements
Timeline:
Repairs are expected to begin in May and continue through July.
Please note: Project timelines are weather-dependent and may change with little notice. We’re working to keep the schedule as accurate and up to date as possible.
| Lot Name | Scheduled Date | Repair |
| Lawrence Tower | May 28 - 29 | Seal Coat/Stripe |
| French Fieldhouse South | May 28 - 30 | Seal Coat/Stripe |
| Ag Admin North | May 28 - 30 | Crack Fill |
| Martha Morehouse West |
May 28 |
Crack Fill |
| Kottman North |
May 29 |
Crack Fill |
| Martha Morehouse Connector |
May 29 - 30 |
Crack Fill |
| Ag Admin South |
May 26 |
Crack Fill |
| Kottman South |
May 30 - 31 |
Crack Fill |
| Print Facility West | May 30 |
Crack Fill |
| Martha Morehouse North |
May 30 - 31 |
Crack Fill |
| Carmack 1 Phase 2 |
May 30 - June 1 |
Crack Fill |
| 1314 Kinnear Road - Assorted Phase 2 |
May 31 - June 1 |
Crack Fill |
| Martha Morehouse East | May 31 - June 1 | Crack Fill |
| Stillman Hall |
June 3 - 4 |
Seal Coat/Stripe |
| Martha Morehouse Staff |
June 4 - 6 |
Crack Fill |
| Print Facility North |
June 4 |
Crack Fill |
| Riverbank North |
June 4 |
Crack Fill |
| 1314 Kinnear Road - Main Phase 2 |
June 6 |
Crack Fill |
| Riverbank South |
June 7 |
Crack Fill |
| Scarlet 2 |
June 8 |
Crack Fill |
| Scarlet 4 |
June 8 |
Crack Fill |
| Scarlet 5 |
June 8 |
Crack Fill |
| Carkmack 6 |
June 12 |
Crack Fill |
| Scarlet 1 |
June 12 |
Crack Fill |
| Scarlet 3 |
June 12 - 13 |
Crack Fill |
| St John Arena |
June 15 - 17 |
Seal Coat/Stripe |
| Animal Science North |
June 16 - 17 |
Crack Fill |
| Animal Science South |
June 16 -17 |
Crack Fill |
| Sisson South |
June 20 - 21 |
Seal Coat/Stripe |
| Carmack 2 Phase 1 |
June 20 - 21 |
Seal Coat/Stripe |
| Carmack 4 |
June 20 - 21 |
Seal Coat/Stripe |
| Buckeye 1 |
June 20 - 21 |
Seal Coat/Stripe |
| Sisson East |
June 22 - 23 |
Crack Fill |
| 1900 Kenny Road - South |
June 23 |
Seal Coat/Stripe |
| 1960 Kenny Road |
June 23 - 24 |
Crack Fill |
| 1900 Kenny Road - North |
June 24 |
Seal Coat/Stripe |
| WHAC Gated |
June 25 - 26 |
Seal Coat/Stripe |
| Sisson North |
June 26 - 27 |
Crack Fill |
| 2000 Kenny Road Lot |
June 27 |
Seal Coat/Stripe |
| Carmack 3 Phase 1 |
June 27 - 28 |
Seal Coat/Stripe |
| Buckeye 5 |
June 27 - 28 |
Crack Fill |
| WHAC North |
June 29 - July 1 |
Seal Coat/Stripe |
| Gray 1 |
July 6 |
Crack Fill |
| Gray 2 |
July 6 |
Crack Fill |
| Gray 4 |
July 7 |
Crack Fill |
| Gray 5 |
July 8 |
Crack Fill |
| Gray 6 |
July 18 - 19 |
Crack Fill |
| Gray 7 |
July 18 - 19 |
Crack Fill |
| Gray 3 |
July 18 - 19 |
Seal Coat/Stripe |
| Carmack 3 Phase 2 |
July 11 - 12 |
Seal Coat/Stripe |
| Buckeye 3 | July 11 - 12 | Crack Fill |
| Stadium Northeast | July 16 - 18 | Seal Coat/Stripe |
| Carmack 2 Phase 2 | July 18 - 19 | Seal Coat/Stripe |
| Buckeye 2 | July 18 - 19 | Crack Fill |
| Buckeye 4 | July 18 - 19 | Crack Fill |
| Blankenship Lot | July 20 - 22 | Seal Coat/Stripe |
Parking-related questions or concerns? Contact CampusParc Customer Care at 614-688-0000 or osuinfo@campusparc.com. We want to help!