Plan ahead for surface parking lot renovations this summer

May 19, 2022

CampusParc will spend a total of $4.97 million this year on parking renovations and improvements, including renovations to more than 80 surface lots.

Surface lot renovations will include either asphalt repairs, crack filling, crack sealing, or striping. Some of the lots will receive a combination of these repairs.

Some repairs may require space closures or full parking lot closures. During these times, please follow posted signage and/or avoid blocked areas to allow work to be completed as quickly as possible. 

When closures are in effect, please use the nearest alternative parking available with your parking permit’s normal access. To view where your permit is valid, please use SureParc on our homepage.

Repairs are scheduled to begin in May and continue through July. A tentative schedule is below. We are working to keep this schedule as updated and accurate as possible, but please keep in mind these project dates are weather dependent and subject to change at a moment's notice.

Renovation work is scheduled during the summer annually to minimize disruption. We apologize for any inconvenience this may cause. 

Questions? Concerns? Contact CampusParc Customer Care at 614-688-0000 or osuinfo@campusparc.com. We want to help! For parking system updates, follow us on Twitter at @CampusParc.

The below information was last updated 6/28/2022 at 10:32 a.m.

Location Start Date Finish Date Repair
Fawcett Center Lot - North 6/27/2022 6/28/2022 Crack fill, seal, stripe
Longaberger ADA Spaces 6/27/2022 6/28/2022 Crack fill, seal, stripe
UniPrint - North 6/28/2022 6/29/2022 Crack fill, seal, stripe
UniPrint - West 6/28/2022 6/29/2022 Crack fill, seal, stripe
Tennis Stadium Lot 6/28/2022 6/29/2022 Crack fill, seal, stripe
Penn Lot 6/29/2022 6/30/2022 Pavement drilling
1900 Kenny Rd - North Lot 6/29/2022 6/30/2022 Crack fill
1900 Kenny Rd - South Lot 6/29/2022 6/30/2022 Crack fill
French Fieldhouse Lot - North 6/30/2022 7/1/2022 Crack fill
French Fieldhouse Lot - South 7/5/2022 7/6/2022 Crack fill
Lawrence Tower Lot 7/5/2022 7/6/2022 Crack fill
Stadium Lot - Northeast 7/6/2022 7/7/2022 Crack fill
Mount Hall Loading Dock 7/11/2022 7/12/2022 Crack fill, seal, stripe
Scott Hall Loading Dock 7/11/2022 7/12/2022 Crack fill, seal, stripe
Evans Hall Lot 7/11/2022 7/12/2022 Crack fill, seal, stripe
Sisson Lot - East 7/11/2022 7/13/2022 Crack fill, seal, stripe
Legal Building 33 West 11th Ave 7/13/2022 7/14/2022 Crack fill, seal, stripe
Letter Lot - Q 7/13/2022 7/14/2022 Crack fill, seal, stripe
Service Annex - East Lot 7/16/2022 7/17/2022 Crack fill
Service Annex - South Spaces 7/16/2022 7/17/2022 Crack fill
Stadium Lot - Southeast 7/16/2022 7/17/2022 Crack fill
Law Lot (Drinko) 7/20/2022 7/21/2022 Crack fill
Large Animal Lot 7/20/2022 7/21/2022 Crack fill
Buckeye Lot 5 7/20/2022 7/23/2022 Crack fill
Northwood & High Lot Complete Crack fill, seal, stripe
Mid-Tower Lot Complete Crack fill, seal, stripe
Carmack Lot 3 Complete Crack fill
Ag Admin - North Complete Crack fill, seal, stripe
2000 Kenny Rd Complete Crack fill
Blankenship Lot Complete Crack fill
Carmack Lot 5 Complete Crack fill, seal, stripe
Carmack Lot 2 Complete Crack fill
Buckeye Lot 3 Complete Crack fill
1224 Kinnear Rd Lot Complete Crack fill

1314 Kinnear - Main Lot

Complete Asphalt
Animal Science Lot - North & South Complete Asphalt
Tuttle Park Place Lot Complete Asphalt

Buckeye Lot 1

Complete

Crack fill

Sisson Lot - North Complete Asphalt
Sisson Lot - South Complete Asphalt
Schumaker Lot Complete Crack fill
Buckeye Lot 4 Complete Crack fill
1314 Kinnear - Assorted Lots Complete Asphalt
Biosciences Underground Lot Complete Asphalt
Student Health/PAES Lot Complete Asphalt
WHAC - Main Lot Complete Crack fill
Plumb Hall East Loop Complete Crack fill
Veterinary Medical Academic - South Lot Complete Crack fill
Vivian Hall Lot Complete Crack fill
1960 Kenny Rd - West Lot Complete Asphalt
Ag Admin - North Complete Asphalt
Scarlet Lot 1 Complete Crack fill
Scarlet Lot 2 Complete Crack fill
WHAC - Gated Lot Complete Crack fill

Ag Admin - South

Complete Crack fill, seal, stripe
Sisson Lot - North  Complete Crack fill, seal, stripe
1314 Kinnear - Main Complete Crack fill, seal, stripe
Letter Lot - O Complete Asphalt
Letter Lot - P Complete Asphalt
Letter Lot - R Complete Asphalt
1100 Kinnear - Main Entrance Complete Crack fill, seal, stripe
1100 Kinnear - North/East Complete Crack fill, seal, stripe
1314 Kinnear - Assorted Areas Complete Crack fill, seal, stripe
1960 Kenny Rd Lot Complete Crack fill, seal, stripe
BioScience Underground Lot Complete Crack fill, seal, stripe
Student Health/PAES Complete Crack fill, seal, stripe
Letter Lot - T Complete Crack fill, seal, stripe
Letter Lot - U Complete Crack fill, seal, stripe
Telecommunications Center Lot Complete Crack fill, seal, stripe
Carmack 5 Lot Complete Asphalt
Ramseyer Lot Complete Crack fill
Arps Hall Lot Complete Crack fill
10th Ave Spaces - Graves Hall Complete Crack fill
Stillman Hall Lot Complete Crack fill
Tuttle Park Place Lot Complete Crack fill, seal, stripe
Carmack Lot 6 Complete Crack fill, seal, stripe
1121 Kinnear Rd Lot Complete Crack fill
Carmack Lot 1 Complete Crack fill, seal, stripe
1315 Kinnear Rd Lot Complete Crack fill
Davis Center Lot Complete Crack fill
Goss Lab Lot Complete Crack fill, seal, stripe
Carmack 6 Lot Complete Asphalt
North Riverbank Complete Asphalt
1900 Kenny Rd - North Lot Complete Asphalt
Longaberger ADA Spaces Complete Asphalt
Sisson Lot - East Complete Asphalt
UniPrint - North Lot Complete Asphalt
North Riverbank Complete Crack fill, seal, stripe
South Riverbank Complete Crack fill, seal, stripe
Buckeye Lot 2 Complete Crack fill
700 Ackerman Rd Lot Complete Crack fill