This article includes garage and surface lot maintenance. Please scroll down to view all impacts.
Please view the full parking impact map for more information.
Preventative Maintenance
CampusParc will begin its annual preventative maintenance program for campus parking garages starting Monday, May 11.
What to expect:
-
Work may take place during the day, overnight, and/or on weekends to reduce disruption.
-
Project length varies depending on the size of the garage and the scope of maintenance.
-
This work is part of CampusParc’s ongoing maintenance program and will continue throughout the summer.
Powerwashing
CampusParc will begin its annual power washing of parking decks, stairwells, and common areas in campus garages on March 21, 2026.
When work will occur:
-
Overnight hours or weekends to reduce disruption
-
Cleaning begins at 7 p.m.
-
The project will continue through August as part of CampusParc’s ongoing maintenance program
-
Duration varies depending on garage size
What to expect:
-
Garages will remain open, but select floors will close on a rolling basis for cleaning
-
Once one floor is completed, the next floor will close until all levels are finished
Important reminder:
-
Vehicles left on closed floors may be relocated at the owner’s expense
-
CampusParc will attempt to contact the vehicle owner before relocation
Below is the tentative schedule for each garage, including the expected impacts.
|
Location |
Preventative Maintenance Dates and Spaces Closed* |
Power Washing Dates and Spaces closed* |
Alternative Parking Options |
|
James Outpatient Care Garage |
N/A |
March 21, 22 |
Carmack Lots |
|
9th Avenue West Garage |
N/A |
March 30 April 1, 2, 3, 4 |
|
|
9th Avenue East Garage |
N/A |
April 6, 8, 9, 10, 11 |
|
|
Old Cannon Garage |
N/A |
April 20-23 April 27, 29 |
9th Avenue West Garage |
|
Wexner Medical Center Garage |
N/A |
May 23-24, May 27-30 June 1, 3, 4, 6 |
|
|
Neil Avenue Garage |
May 11 – August 14 50 spaces |
July 20-23 July 26-27 |
|
|
12th Avenue Garage |
May 11 – August 14 120 spaces |
August 28-30 |
|
|
Arps Garage |
May 11 – August 14 491 spaces |
August 14-17 |
|
|
SAFEAUTO Garage |
May 11 – August 7 125 spaces |
August 19-23 Weekend closure |
|
|
Union South Garage |
May 11 – August 14 150 spaces, full & partial weekend closures |
August 25 - 27 |
|
|
Gateway Garage |
May 11 – August 14 550 spaces, L4 & L5 closed |
August 14 - 17 |
A-Permit Holders: |
|
Lane Avenue Garage |
May 11 – August 7 200 spaces |
July 31 August 1 August 4-9 |
West Lane Avenue (BG4 Permit holders) |
|
Northwest Garage |
N/A |
June 8-11 |
|
|
Tuttle Garage |
N/A |
June 15, 17-20, 22 |
|
|
Ohio Union North Garage |
N/A |
June 29, 30 July 1-2 |
|
|
West Lane Garage |
N/A |
July 30 |
|
|
11th Avenue Garage |
N/A |
August 10-12 |
*Please note: Dates are subject to change.
We apologize for any inconvenience this may cause and appreciate your understanding as we work to improve the garage's condition as part of our annual maintenance plan.
Surface Lot Maintenance
What’s happening:
Surface parking lot renovations take place annually after the spring semester ends as part of CampusParc's annual preventative maintenance.
Scheduling this work during the summer helps reduce the impact on customers, as fewer students, faculty, and staff are on campus.
What the work includes:
-
Asphalt repairs
-
Crack filling and sealing
-
Lot striping
-
Some lots will receive a combination of these improvements
Timeline:
Repairs are expected to begin in May and continue through July. A work schedule is being finalized and will be published as soon as possible.
Keep in mind:
Project timelines are weather-dependent and may change with little notice.
| Lot Name | Scheduled Date | Repair |
|
1224 Kinnear Road Lot |
Seal Coat/Stripe |
|
|
1315 Kinnear Road Lot |
Seal Coat/Stripe |
|
|
1900 Kenny Road Lot - North |
Seal Coat/Stripe |
|
|
1900 Kenny Road Lot - South |
Seal Coat/Stripe |
|
|
2000 Kenny Road Lot |
Seal Coat/Stripe |
|
|
Arps Hall Lot |
Seal Coat/Stripe |
|
|
Blankenship Lot |
Seal Coat/Stripe |
|
|
Buckeye Village |
Seal Coat/Stripe |
|
|
Carmack 2 |
Seal Coat/Stripe |
|
|
Carmack 3 |
Seal Coat/Stripe |
|
|
Carmack 4 |
Seal Coat/Stripe |
|
|
French Fieldhouse North |
Seal Coat/Stripe |
|
|
French Fieldhouse South |
Seal Coat/Stripe |
|
|
Ice Rink Lot |
Seal Coat/Stripe |
|
|
Lawrence Tower Lot |
Seal Coat/Stripe |
|
|
ROTC Lot |
Seal Coat/Stripe |
|
|
St John Arena Lot |
Seal Coat/Stripe |
|
|
Stadium Northeast |
Seal Coat/Stripe |
|
|
Stadium Southeast |
Seal Coat/Stripe |
|
|
Stillman Hall Lot |
Seal Coat/Stripe |
|
|
West Defiance Drive Lot |
Seal Coat/Stripe |
|
|
West Defiance Drive Spaces |
Seal Coat/Stripe |
|
|
WHAC Gated |
Seal Coat/Stripe |
|
|
WHAC Main |
Seal Coat/Stripe |
|
|
1100 Kinnear Road - Maint Entrance |
Crack Fill |
|
|
1100 Kinnear Road - North/East |
Crack Fill |
|
|
1314 Kinnear Road Lot - Assorted |
Crack Fill |
|
|
1314 Kinnear Road Lot - Main |
Crack Fill |
|
|
1960 Kenny Road Lot |
Crack Fill |
|
|
Ag Admin North |
Crack Fill |
|
|
Ag Admin South |
Crack Fill |
|
|
Animal Science North |
Crack Fill |
|
|
Animal Science South |
Crack Fill |
|
|
BioScience Underground?? |
Crack Fill |
|
|
Buckeye 1 |
Crack Fill |
|
|
Buckeye 2 |
Crack Fill |
|
|
Buckeye 3 |
Crack Fill |
|
|
Buckeye 4 |
Crack Fill |
|
|
Buckeye 5 |
Crack Fill |
|
|
Carmack 1 |
Crack Fill |
|
|
Carmack 5 |
Crack Fill |
|
|
Carkmack 6 |
Crack Fill |
|
|
Davis Center Lot |
Crack Fill |
|
|
Evans Hall Lot |
Crack Fill |
|
|
Goss Lab Lot |
Crack Fill |
|
|
Gray 1 |
Crack Fill |
|
|
Gray 2 |
Crack Fill |
|
|
Gray 3 |
Crack Fill |
|
|
Gray 4 |
Crack Fill |
|
|
Gray 5 |
Crack Fill |
|
|
Gray 6 |
Crack Fill |
|
|
Gray 7 |
Crack Fill |
|
|
JOC West |
Crack Fill |
|
|
JOC South |
Crack Fill |
|
|
Kottman North?? |
Crack Fill |
|
|
Kottman South?? |
Crack Fill |
|
|
Legal Bldg 33 West 11th Ave |
Crack Fill |
|
|
Longaberger Accessible Spaces |
Crack Fill |
|
|
Lot L |
Crack Fill |
|
|
Lot M |
Crack Fill |
|
|
Lot Q |
Crack Fill |
|
|
Lot S |
Crack Fill |
|
|
Lot T |
Crack Fill |
|
|
Lot U |
Crack Fill |
|
|
Lot W |
Crack Fill |
|
|
Martha Morehouse Connector |
Crack Fill |
|
|
Martha Morehouse North |
Crack Fill |
|
|
Martha Morehouse East |
Crack Fill |
|
|
Martha Morehouse Southwest |
Crack Fill |
|
|
Martha Morehouse Staff |
Crack Fill |
|
|
Martha Morehouse West |
Crack Fill |
|
|
Print Facility North |
Crack Fill |
|
|
Print Facility West |
Crack Fill |
|
|
Ramseyer Hall Lot |
Crack Fill |
|
|
Ramseyer Hall Lot West |
Crack Fill |
|
|
Riverbank North |
Crack Fill |
|
|
Riverbank South |
Crack Fill |
|
|
Scarlet 1 |
Crack Fill |
|
|
Scarlet 2 |
Crack Fill |
|
|
Scarlet 3 |
Crack Fill |
|
|
Scarlet 4 |
Crack Fill |
|
|
Scarlet 5 |
Crack Fill |
|
|
Scott Hall Loading Dock |
Crack Fill |
|
|
Service Annex East |
Crack Fill |
|
|
Service Annex South |
Crack Fill |
|
|
Sisson East |
Crack Fill |
|
|
Sisson North |
Crack Fill |
|
|
Sisson South |
Crack Fill |
|
|
Student Health/PAES |
Crack Fill |
|
|
Telecommunications Network |
Crack Fill |
|
|
Tennis Stadium Lot |
Crack Fill |
|
|
Tuttle East Lot |
Crack Fill |
|
|
BRT Loading Dock |
Surface Repair |
|
|
Longaberger Loading Dock |
Surface Repair |
|
|
Lot R |
Surface Repair |
Parking-related questions or concerns? Contact CampusParc Customer Care at 614-688-0000 or osuinfo@campusparc.com. We want to help!