CampusParc is scheduled to begin its annual power washing of the parking decks, stairwells, and common areas of campus garages on Sunday, May 22. This deep clean includes the pretreating of all oil spots with a degreasing agent, followed by a high-pressure rinse at 4,000 psi. All water is recovered and disposed of in accordance with Ohio EPA guidelines.
Power washing of garages occurs during the late and overnight hours or on weekends to minimize disruption to customers. The size of the garage and number of spaces dictate the number of days that are needed to complete the power washing. This work, which is part of CampusParc’s ongoing maintenance program, will continue through August.
Each garage will be impacted by one or both of the following:
- Rolling deck closures: The garage will remain open but select floors will close for nightly cleaning. Cleaning starts at 7 p.m. At 5 a.m. the following day, these floors will reopen and spaces on the subsequent floor(s) will close. This will continue until the cleaning of all affected floors is complete.
- Full closure: The garage will fully close. On the start date, garage entrances will close at 4 p.m. and all vehicles remaining parked in the garage must exit by 7 p.m. The garage will reopen at 5 a.m. on the end date.
Vehicles remaining in these areas after closure are subject to relocation at the owner’s expense.
A tentative schedule for each garage, as well as the type of impact, is as follows:
Garage | Start Date | End Date | Impact |
Wexner Medical Center | Sunday, May 22 | Saturday, May 28 | Rolling Deck Closures |
West Lane Avenue | Tuesday, May 31 | Wednesday, June 1 | Rolling Deck Closures |
Lane Avenue | Thursday, June 2 | Friday, June 3 |
Rolling Deck Closures |
Friday, June 3 | Monday, June 6 |
Full Closure |
|
Ohio Union North | Monday, June 13 | Wednesday, June 15 | Rolling Deck Closures |
12th Avenue | Friday, June 17 | Monday, June 20 | Full Closure |
Northwest | Wednesday, June 22 | Friday, June 24 | Rolling Deck Closures |
11th Avenue | Tuesday, July 5 | Thursday, July 7 | Rolling Deck Closures |
9th Avenue East | Friday, July 8 | Monday, July 11 | Full Closure |
Arps | Tuesday, July 12 | Friday, July 15 | Rolling Deck Closures |
Gateway | Monday, July 18 | Friday, July 22 | Rolling Deck Closures |
9th Avenue West | Friday, July 29 | Monday, Aug. 1 | Full Closure |
SAFEAUTO | Friday, Aug. 5 | Monday, Aug. 8 | Full Closure |
Ohio Union South | Tuesday, Aug. 9 | Friday, Aug. 12 | Rolling Deck Closures |
Neil Avenue† | TBD | TBD | - |
Tuttle† | TBD | TBD | - |
†Power washing schedules for these garages will be impacted by renovation projects. Additional details will be provided at a later date.
Please note: Dates are subject to change.