Tuttle Garage Elevator Modernization Project to Begin Monday, 5/21

Apr 23, 2018

On Monday, May 21, work will begin to modernize elevators in Tuttle Park Place Garage. New elevator cars will be installed, and each elevator shaft will be renovated accordingly.

During the work, part of CampusParc’s ongoing capital improvements process, one elevator will remain in service while the other is being renovated. The southeast elevator will be taken out of service on Monday, May 21, and is expected to return to service on Monday, July 23. The northwest elevator is scheduled to be taken out of service on Monday, July 23, and is expected to return to service on Friday, October 12.